Business

Business
Field

LS Marine Solution, a future leader connecting the world

Track Record

2021 ~ 2022

Jeonnam Offshore Wind Power Project

General
  • PeriodJun. 09, 2022 ~ Sep. 30, 2024
  • ClientJeonnam Offshore Wind Power
Project Summary
  • Type of WorkOffshore wind power submarine cable sector (EPCi)

Technical support for underwater installation of acoustic sensor for remote detection (Sea Area A)

General
  • PeriodApr. 12, 2022 ~ Jan. 15, 2024
  • ClientLIG Nex1
Project Summary
  • Type of WorkSite survey and support for the design of installation method

Service for acquisition of license for underwater installation of acoustic sensor for remote detection (Sea Area A)

General
  • PeriodApr. 12, 2022 ~ Jan. 15, 2024
  • ClientLIG Nex1
Project Summary
  • Type of WorkDiagnosis of maritime traffic safety and consultation on general sea area use

ㅇㅇ-I Sensor Repair Works (vessel)

General
  • PeriodAug. 31, 2022 ~ Dec. 25, 2022
  • ClientLIG Nex1
Project Summary
  • Type of WorkCable Recovery, Installation & Lay

DSCPA2 Palawan Reciliency Project

General
  • PeriodAug. 23, 2022 ~ Dec. 18, 2022
  • ClientFiberHome Phils., Inc.
Project Summary
  • Type of WorkCable Lay

DSCPA2 Project

General
  • PeriodFeb. 04, 2022 ~ Aug. 08, 2022
  • ClientFiberHome Phils., Inc.
Project Summary
  • Type of WorkCable Lay

TPKM2 Replacement Project

General
  • PeriodFeb. 23, 2022 ~ Jun. 29, 2022
  • ClientNEC Corporation
Project Summary
  • Type of WorkCable Installation & Lay

CDSCN Project

General
  • PeriodJan. 03, 2022 ~ May. 17, 2022
  • ClientOMS GROUP SDN. BHD.
Project Summary
  • Type of WorkCable Lay

ㅇㅇ-I/ㅇㅇ-II/ㅇㅇ-V Sensor Maintenance Work (vessel)

General
  • PeriodMay. 17, 2021 ~ Apr. 30, 2022
  • ClientLIG Nex1
Project Summary
  • Type of WorkCable Recovery, Installation & Lay

Tamna Offshore Wind Power (onshore section reinforcement work of submarine cable)

General
  • PeriodAug. 28, 2021 ~ Oct. 31, 2021
  • ClientDoosan Heavy Industries
Project Summary
  • Type of WorkCable Reinforcement Work

ECHO Project

General
  • PeriodAug. 26, 2021 ~ Nov. 30, 2022
  • ClientNEC
Project Summary
  • Type of WorkCable Installation & Lay

Submarine cable installation that connects Jeju and Udo

General
  • PeriodAug. 05, 2021 ~ Sep. 30, 2022
  • ClientSK Telecom
Project Summary
  • Type of WorkLicensing / Procurement / Cable Installation

SJC2 Project

General
  • PeriodNov. 01, 2021 ~ Jun. 30, 2022
  • ClientNEC
Project Summary
  • Type of WorkCable Installation & Lay

NCP PLIB S1.1, S3 Project

General
  • PeriodMar. 27, 2021 ~ Dec. 31, 2022
  • ClientSubcom
Project Summary
  • Type of WorkCable Lay

NW Russia Project

General
  • PeriodNov. 04, 2019 ~ Feb. 15, 2021
  • ClientHuawei Marine Networks Co., Limited
Project Summary
  • Type of WorkCable Installation & Lay