LS Marine Solution, a future leader connecting the world

Track Record

1997 ~ 1998

Domestic Power Cable Repair

  • Position of obstacleRepair of Power Cable between Heukil-do and Masak-do, Cheonnam
  • Period of RepairAgu. 26 ~ Agu. 31, 1998

FLAG Seg.P2 Inspection

  • Position of obstacleGeoje Coast
  • Period of RepairDec. 15 ~ Dec. 16, 1998
  • Cause of obstaclesKendrick (chartering)

FLAG Seg.P3 Retro-Burial #4

  • Position of obstacle111km position from Nakhodka
  • Period of RepairDec. 7 ~ Dec. 14, 1998
  • Cause of obstaclesKendrick (chartering)

FLAG Seg.P3 Repair #4

  • Position of obstacle111.8km position from Nakhodka
  • Period of RepairNov. 29 ~ Dec. 7, 1998
  • Cause of obstaclesSegyero

RJK Seg.B1 REPAIR #1

  • Position of obstacle440km position from Nakhodka
  • Period of RepairNov. 12 ~ Nov. 22, 1998
  • Cause of obstaclesSegyero

RJK Seg.B3 Retro-Burial #3

  • Position of obstacle7km position from Busan (water depth:65m)
  • Period of RepairOct. 22 ~ Nov. 4, 1998
  • Cause of obstaclesKendrick (chartering)

RJK Seg.B3 Retro-Burial #3

  • Date of obstacleSep. 8, 1998
  • Repair VesselSegyero
  • Period of RepairOct. 1 ~ Oct. 9, 1998 (for 9days)
  • Position of obstacle7 km position from Busan cable station (water depth:65m)
  • Cause of obstaclesFishing

Ullung-Mainland #3 Repair

  • Date of obstacleJul. 22, 1998
  • Repair VesselSegyero
  • Period of RepairJul. 28 ~ Agu. 6, 1997(for 10days)
  • Position of obstacle56.6 km position from Hosan cable station (water depth:1,800m)
  • Cause of obstaclesFishing

Post Retro-burial work FLAG P3 Repair(Shanghai)

  • Date of contractMay. 19, 1998
  • Contracting PartiesFLAG/kt submarine
  • 1 burial work6,342m
  • PositionOffshore in China
  • 2 burial work1,893m
  • Position74 km position from Shanghai, China
  • 3 burial work958Km
  • PositionShanghai, China

Korea Electric Power Cable Repair

  • Work installation#1 cable between Heukildo and Masakdo
  • Cable length3,674m
  • Period of Repair1998
  • Repair VesselSegyero
  • Laying lenth182m

The 1st Cheju-Koheung Retro-Burial #8

  • Position of obstacle23.9km position from Jeju (water depth:135Km)
  • Period of RepairOct. 20 ~ Nov. 25, 1997
  • Repair VesselsM V Big Orange (chartering)

1st Cheju-Mainland #8 Repair

  • Date of obstacleSep. 17, 1997
  • Period of RepairOct. 14 ~ Oct. 19, 1997 (for 6days)
  • Position of obstacle23,863km position from Jeju cable station(water depth:135km)
  • Repair VesselC.S.IRIS (Gross tonnage of 3,800, C&W-M, England)
  • Cause of obstaclesFishing

1st Cheju-Mainland #7 Repair

  • Date of obstacleJul. 21, 1997
  • Period of RepairJul. 28 ~ Agu. 8, 1997 (for 11days)
  • Position of obstacle18.9km position from Jeju BM (water depth:130m)
  • Repair VesselC.S.IRIS (Gross tonnage of 3,800, C&W-M, England)
  • Cause of obstaclesFishing

R-J-K Cable Repair

  • Date of obstacleMar. 11, 1997
  • Period of RepairMar. 19 ~ Mar. 28, 1997 (for 10days)
  • Position of obstacle174km position from Busan (water depth:2,000m)
  • Repair VesselIRIS (Gross tonnage of 3,800, C&W-M, England)
  • Cause of obstaclesFishing